MBTA Board approves Capital Investment Plan for Fiscal Years 2023-2027

Support LCTV with your membership

The Fiscal Year 2023-2027 MBTA Capital Improvement Plan includes all planned capital investments over the next five years.

The MBTA Board of Directors today approved the Fiscal Year 2023-2027 MBTA Capital Improvement Plan (FY23-27 MBTA CIP). The FY23-27 MBTA CIP includes over 500 unique capital projects to modernize, expand, and increase the reliability of the MBTA transit network. 

“With the goal of improving reliability, modernizing the system, expanding capacity and the network, and continuing to make critical safety improvements, the MBTA’s five-year CIP is an important document that guides our investment planning,” said MBTA General Manager Steve Poftak. “I thank the Board for approving of our CIP, and I thank our riders and the public for participating in this public process and letting us know what kinds of capital investments they’d like to see the MBTA prioritize for investment.” 

The FY23-27 MBTA CIP is available at mbta.com/cip and includes an overview of the Authority’s capital planning process, summaries of investment programs, summaries of investments by mode, and the full list of capital projects.

A short-term, financially constrained investment program updated annually, the FY23-27 MBTA CIP is driven by the following goals:

  • Improve the reliability of the MBTA’s transit system and modernize existing assets to accommodate current or anticipated growth.
  • Make targeted investments in the expansion of the transportation network to increase capacity or provide riders with more options across transit modes.

For more information, visit mbta.com/CIP or connect with the T on Twitter @MBTA, Facebook /TheMBTA, or Instagram @theMBTA.

_______________________________


CAPITAL INVESTMENTS FOR LYNN

Photo courtesy of The MBTA

The following information was sourced from the FY 2023 – 2027 CIP document. Below are the portions mentioning Lynn, please click here to download the full document as a PDF.

Note: Some CIP projects may show $0 programmed spend in FY23-27 as they are expected to complete in FY22 but are not yet formally finalized or closed out.

Emergency Egress Ventilation and Lighting (P1001)

Design of life safety systems improvements (emergency egress lighting, backup generators, ventilation, fire hydrants and partitions) at Cabot, Fellsway, Lynn, Charlestown, Albany, and Southampton bus garages and Reservoir and Riverside car houses.

Primary mode/line | Multimodal
Current phase | Design
FY 23-27 Programmed Spend | $0.6M
Total Authorized budget | $1.0M

_______________________________

Bridge Bundling Contract (P0495)

Replacement of six commuter rail bridges at Intervale Rd. in Weston; Bacon St. in Wellesley; High Line Bridge in Somerville; Lynn Fells Parkway in Melrose; Parker St. in Lawrence; and Commercial St. in Lynn.

Primary mode/line | System-wide
Current phase | Construction
FY 23-27 Programmed Spend | $65.3M
Total Authorized budget | $132.2M

_______________________________

Shared Streets (boston, Somerville and Lynn (P0953c)

Design and construction of three bus lane corridors on Washington St (Somerville), North Washington St (Boston), and Western Ave (Lynn). Includes lane pavement markings, flex posts, signage, traffic signals and transit signal priority.

Primary mode/line | Bus
Current phase | Construction
FY 23-27 Programmed Spend | $0.1M
Total Authorized budget | $0.7M

_______________________________

Photo courtesy of The MBTA
Lynn Station Direct Fixation Repairs Track 1 & Station Amenities (P0632)

Removal of existing tracks and concrete base for the installation of two new tracks on wooden ties at Lynn Commuter Rail Station. Includes land purchase in Lynn for project development.

Primary mode/line | Commuter Rail
Current phase | Construction
FY 23-27 Programmed Spend | $0M
Total Authorized budget | $1.8M

_______________________________

Lynn Parking Garage Decommissioning (P1025)

Decommissioning of the closed Lynn Station parking garage.

Primary mode/line | Commuter Rail
Current phase | Pre-design
FY 23-27 Programmed Spend | $11.0M
Total Authorized budget | $11.0M

_______________________________

Lynn Parking Garage Phase 1 (P0090)

Elevator, waterproofing, HVAC, electrical, plumbing, and fire protection system improvements at Lynn Station and parking garage.

Primary mode/line | Commuter Rail
Current phase | Closeout
FY 23-27 Programmed Spend | $0.3M
Total Authorized budget | $6.6M

_______________________________

Lynn Station Improvements Phase II (R0071)

Design funding for new elevators, stairs, platform, canopy, and architectural improvements to the station and the intent to acquire and demolish structures under station’s viaduct.

Primary mode/line | Commuter Rail
Current phase | Design
FY 23-27 Programmed Spend | $14.8M
Total Authorized budget | $16.5M


The above information was submitted to us by the MBTA.